1) Run a heavy wire from a 'U' terminal from to the first transformer to a 'U' terminal of the second. Do not connect any other terminals together.
2) Plug both transformers into a power strip and turn on. Just because they're on the same strip, DOESN'T GUARANTEE they're in phase. Proceed to step 3 regardless.
3) Turn voltage up on both transformers to about the same voltage. Doesn't really matter WHAT voltage, just so they're the SAME voltage. Use the AC setting on a voltmeter to measure, even an elcheapo digital voltmeter will do. No spark testing!. I usually go around 12VAC each.
4) Measure between the two outputs. If the outputs are near or at ZERO then PHASED. If Outputs are near double the setting in (step 3) then OUT OF PHASE.
5) If out of phase, reverse the plug to the power strip of ONE transformer, then measure again. Put a small mark on the plug of both transformers to remember how they plug in.