Following Steve's "year in review" theme, here are some pics which represent the major additions/changes to our club layout during 2014.
We jumped into a signal system with both feet using Custom Signals
We installed the last two bridges over our "great gorge" area
The last one is still getting some finishing touches
Requiring restricted speeds
The platforms under our passenger station at the south end were finished.
The river that runs through the "great gorge" terminates with this water scene
We installed a video system to monitor trains as they run through blind spots that are not visible from the control tower
Much progress made on Phase 1 of the city at the south end
Scenery work began in the steam service facility starting with detailing of the turntable bridge
Construction of our 5 bay diesel shop was started
A very productive year. Wishing everyone health and happiness in the New Year