Skip to main content

I know this is the first ever post started on Atlas track and your all excited.. so here we go.

 

When it comes to sanding the middle rail, why do you do this?

I am assuming for conductivity problems.. does this need to be done with new track or only if you start to experience problems?

If it does need to be done to new track, then why do they even finish the top of the rail?

 

When it comes to the switches and track planning.. typically should the #5 switches be used for connecting main lines on a straight run, and then use O72 switches in other areas such as yards?

 

When it comes to switch machines from atlas switches, I have heard everyone use everything from Z-stuff to tortise, to just staying with the atlas. I plan on mounting the machines under the table. What should I plan on using for this? FYI I am planning on using DCS and Legacy to control switches.

 

Finally, it seems that everyone has agreed that track spacing should be 6" center rail to center rail to accommodate any engine and not run into clearance issues. Do you use this measurement on straights as well, or just on curves. I am wondering this because there is an area where I want to try to fit 3 lines closer to each other on a straight run but I dont want to cause problems.

 

Thanks in advance for your replies. This is my first layout I will be constructing since like 1997, and first time using other than tubular track.... and first time using DCS or Legacy to wire switches........ lots of unknowns.

Last edited by Zett
Original Post

Replies sorted oldest to newest

Zett,

 

I use Atlas track on my 28' x 45' layout out of the box with out any sanding to the middle rail.  I really have not had any noticeable conductivity issues.  I run DCS, and have had good operating luck.  I do not run TMCC or Legacy at this point so I can't comment if this is an issue with those systems. 

 

On switches, I use a mostly O72, I have some #7's, and a curved O72/O54.  My yard is all O72.  These have worked well.   I use the Atlas switch motors, and currently they are on top of the table.  Most work well, there are a few older ones that some tie hang up, but tat seems to be rare.

 

On straight sections I have spaced the rails much closer than 6" and had no issues.  On the curves I do try to give about 6" or a bit more to allow room.  Most of my curves are O81 -O90 with a minimum of O72.

 

I hope this helps

I plan to use 3.5" to 4" in the yard, 4" on main line straights and 5.5-6" on curves, depending on the radius of the track. I will run articulateds and passenger cars so clearences will be checked! I am using Gargraves track with Ross switches. I will most likely use #6 for mainline cross overs and maybe #4's in the yard. I have some o-72 and 84's for sidings and such.

Tortise switch machines work when installed correctly. We used many of them on the n scale layout we built. The built in contacts really help with signals or power feeding the switch. I will use the 1000 switch machine tied into the AIU for remote actuation.

Frank

Thanks for the replies. I am glad that I can go closer than 6" on the straights.

 

Rich what made you choose to use an O72 to connect two straight lines rather than a #5? Maybe I am over thinking this. I have to go inspect your layout post again.

 

With the O-72, O54 curved switch you have... do you run any engines with an O-72 minimum over the O-54 curve? I was thinking of using it in one area, but then I have to pay attention to what engines I can and cannot run over this area.

When it comes to sanding the middle rail, why do you do this?

I am assuming for conductivity problems.. does this need to be done with new track or only if you start to experience problems?

When you experience problems. It's no big deal with wiping the tops with Scotchbrite Pad.

 

If it does need to be done to new track, then why do they even finish the top of the rail?

Because it's too costlyin the mfg process  to omit the top of the rail with the coating.

 

When it comes to the switches and track planning.. typically should the #5 switches be used for connecting main lines on a straight run, and then use O72 switches in other areas such as yards?

You would use #5 for high speed switches on long straight sections. IT is a better  for a train to cross over at a higher speed than the 072 switch.

 

When it comes to switch machines from atlas switches, I have heard everyone use everything from Z-stuff to tortise, to just staying with the atlas. I plan on mounting the machines under the table. What should I plan on using for this? FYI I am planning on using DCS and Legacy to control switches.

 

IF you are going underneath with switch machines and you have room. go tortoise switch machine.

 

Originally Posted by Zett:

I know this is the first ever post started on Atlas track and your all excited.. so here we go.

 

When it comes to sanding the middle rail, why do you do this? Newer Atlas track is not a problem. Some of the original track about 10 years ago, the black would actually roll-up on the engine third rail contact. I am assuming for conductivity problems.. does this need to be done with new track or only if you start to experience problems? Atlas flat top rail tends to be a bit problematic when it comes to dirt/dust. The normal tubular or small crown top rail will push the dirt aside and down off the rail.  A light coating of dust on the Atlas rail rolls-up on the contact.  Easily corrected with some sort of a track cleaning car used before major running. If it does need to be done to new track, then why do they even finish the top of the rail? Probably not cost effective to blacken just the sides.  

When it comes to the switches and track planning.. typically should the #5 switches be used for connecting main lines on a straight run, and then use O72 switches in other areas such as yards? Atlas has a pretty good selection of switches/crosses and other accessory parts.  Best to review there track catalog.  

When it comes to switch machines from atlas switches, I have heard everyone use everything from Z-stuff to tortise, to just staying with the atlas. I plan on mounting the machines under the table. What should I plan on using for this? FYI I am planning on using DCS and Legacy to control switches.  Atlas has there own under table switch motor.  Each switch comes with a motor, I'm not sure what type of deal would be involve in swapping motors for their under table motor. There is also a very popular #6924 universal relay board that has a lot of good purposes and a new #57 switch control button.   There are also some nice track side lighting accessories such as the #6931 dwarf lights that can be integrated into the install relatively easily.  

Finally, it seems that everyone has agreed that track spacing should be 6" center rail to center rail The Atlas fixed curve pieces are designed for 4.5"track spacing center to center. O-27, 36, 45, 54, 63, 72, etc. Flex track is available but difficult to use My layout is 95% O-54 and smaller.  I've never had a problem with the 4.5" spacing. to accommodate any engine and not run into clearance issues. Do you use this measurement on straights as well, or just on curves. I am wondering this because there is an area where I want to try to fit 3 lines closer to each other on a straight run but I dont want to cause problems.

 

Thanks in advance for your replies. This is my first layout I will be constructing since like 1997, and first time using other than tubular track.... and first time using DCS or Legacy to wire switches........ lots of unknowns.   Let me post this and do some editing.  I need to get to the Atlas Website to insert some links.  I have yet to do this via the newer forum and have to open the Atlas site via a tab to insert pictures and links.  Bare with me on this, I need the practice.  It also appears I don't have access to the insert/edit link button in the tool bar.

 Here is a few link to the Atlas site that would be of help

Atlas Right Track (Freeware) version 10.0.  Design software supplied by Atlas.

Atlas wiring diagram for the 6924 Universal relay board.

Atlas #57 switch controller.

 

Atlas 6098 Delux undertable switch machine.

 

Atlas 6931 dwarf lights.

 

Last edited by Mike CT
Zett, On a previous layout, I used Atlas 072 turnouts "cut 12 degree" to connect two mainlines.  Cutting Atlas switches this way is common enough, that RR Track software has it as an option.  I had a lot of good, and bad experience with Atlas Nickel Silver track.  If you'd like to read more you can check out the following links.  Best of luck, Bob C
 
 
 

I know this is the first ever post started on Atlas track and your all excited.. so here we go.

 

When it comes to sanding the middle rail, why do you do this?

I am assuming for conductivity problems.. does this need to be done with new track or only if you start to experience problems?

If it does need to be done to new track, then why do they even finish the top of the rail?

 

When it comes to the switches and track planning.. typically should the #5 switches be used for connecting main lines on a straight run, and then use O72 switches in other areas such as yards?

 

When it comes to switch machines from atlas switches, I have heard everyone use everything from Z-stuff to tortise, to just staying with the atlas. I plan on mounting the machines under the table. What should I plan on using for this? FYI I am planning on using DCS and Legacy to control switches.

 

Finally, it seems that everyone has agreed that track spacing should be 6" center rail to center rail to accommodate any engine and not run into clearance issues. Do you use this measurement on straights as well, or just on curves. I am wondering this because there is an area where I want to try to fit 3 lines closer to each other on a straight run but I dont want to cause problems.

 

Thanks in advance for your replies. This is my first layout I will be constructing since like 1997, and first time using other than tubular track.... and first time using DCS or Legacy to wire switches........ lots of unknowns.

Zett: I was mistaken, the Atlas 072 turnout is cut 19.5 degrees, to connect two parallel tracks at approximately 4 to 4.5 inches apart.  I just checked my RR Track software to confirm.

I know this is the first ever post started on Atlas track and your all excited.. so here we go.

 

When it comes to sanding the middle rail, why do you do this?

I am assuming for conductivity problems.. does this need to be done with new track or only if you start to experience problems?

If it does need to be done to new track, then why do they even finish the top of the rail?

 

When it comes to the switches and track planning.. typically should the #5 switches be used for connecting main lines on a straight run, and then use O72 switches in other areas such as yards?

 

When it comes to switch machines from atlas switches, I have heard everyone use everything from Z-stuff to tortise, to just staying with the atlas. I plan on mounting the machines under the table. What should I plan on using for this? FYI I am planning on using DCS and Legacy to control switches.

 

Finally, it seems that everyone has agreed that track spacing should be 6" center rail to center rail to accommodate any engine and not run into clearance issues. Do you use this measurement on straights as well, or just on curves. I am wondering this because there is an area where I want to try to fit 3 lines closer to each other on a straight run but I dont want to cause problems.

 

Thanks in advance for your replies. This is my first layout I will be constructing since like 1997, and first time using other than tubular track.... and first time using DCS or Legacy to wire switches........ lots of unknowns.

Thanks for the replies. I think I am just going to have to order some #5s, and #7s and then plan from there. For sure on main lines I am going with a 5 or a 7, the 72 seems like too much of a curve.

 

I tried planning with the track software but I need to hold the product.

 

Trevize when you use #5s in the yard, how much spacing does that leave between the lines center to center?

 

Mr. Muffin, I gave considerable thought to using Ross but I decided to go Atlas. I see a lot of newer layouts on here sticking with the atlas switches and am hearing less and less complaints. I think the difference in tie size would drive me nuts.

Zett: I'm sorry my response has been disjointed, it's been awhile since I thought about Atlas switches.  The primary reason to use a pair of "cut" 072 switches for a crossover instead of #5s, or other similar turnouts, is to save distance on your layout.  Two cut Atlas 072s end to end, will be significantly shorter in overall length as a crossover than two #5s end to end.  This can be important if you have only limited lengths of straight track in which to accomplish the crossover.  If distance is not a problem, then the #5 or other similar turnout is a better choice fro crossovers.  Another point, if you have not already purchased the Atlas track products, you may want to look at other alternatives.  If you looked at the two links I previously noted, you'll see I have significant experience with Atlas Nickel Silver track.  You'll also note that on my most recent layout, I dumped Atlas turnouts for Ross Custom Switches.  I have mated the Ross products to hundreds of feet of salvaged Atlas track.  If I were starting fresh, I'd look at the MTH Real Trax, or consider using Gargraves, with Ross switches.  Good luck with your project.

I know this is the first ever post started on Atlas track and your all excited.. so here we go.

 

When it comes to sanding the middle rail, why do you do this?

I am assuming for conductivity problems.. does this need to be done with new track or only if you start to experience problems?

If it does need to be done to new track, then why do they even finish the top of the rail?

 

When it comes to the switches and track planning.. typically should the #5 switches be used for connecting main lines on a straight run, and then use O72 switches in other areas such as yards?

 

When it comes to switch machines from atlas switches, I have heard everyone use everything from Z-stuff to tortise, to just staying with the atlas. I plan on mounting the machines under the table. What should I plan on using for this? FYI I am planning on using DCS and Legacy to control switches.

 

Finally, it seems that everyone has agreed that track spacing should be 6" center rail to center rail to accommodate any engine and not run into clearance issues. Do you use this measurement on straights as well, or just on curves. I am wondering this because there is an area where I want to try to fit 3 lines closer to each other on a straight run but I dont want to cause problems.

 

Thanks in advance for your replies. This is my first layout I will be constructing since like 1997, and first time using other than tubular track.... and first time using DCS or Legacy to wire switches........ lots of unknowns.

Thanks for clearing up the discussion on the O-72. I may use that as an option on the back side of the layout.

 

I really put a lot of thought into the track choice, but I just really made a final decision after watching so many layouts coming together using Atlas track and switches, Eric Siegel, Chugman, BNSF Mike (even though no updates lately, where are you Mike?) Ingeniero (who it looks like is using both Atlas and Ross) Rich883... thats just off the top of my mind.

Zett,

 

Haven't read through all the replies above...  I was doing pretty good up until the purple text on the dark grey background.  OUCH!!!        My eyes are still recovering from that.

 

Anyway, I'll quickly cut to the chase on a few key concepts here...

 

First, the cool thing about Atlas-O track is that it is a SYSTEM.  Except for very special arrangements, you shouldn't need to do too much in the way of cutting special fitter pieces if you plan ahead with layout design software like RR-Track.

 

Second, for mainline parallel track spacing, do NOT use O72 switches... rather use the numbered #5 or #7.5 switches which give you 4.5" center-to-center spacing and a much more prototypical "look".  Then if your minimum curve on the inside loop is O72, your next loop would be O81 and the third loop would be O90, and so on.  You wouldn't need to cut flex track for any of this... it's all stock, unless you're going above O-108.   And the stock pieces maintain 4.5" track spacing throughout.

 

As far as switch machines... I'd recommend Tortoise if you're inclined to mount switch marchines underneath the table-top.  On the plus side for Tortoise, the slow movement of the points is very prototypical compared to the quick-action snap motion of most brands on the market.  However, the Tortoise needs constant power applied until the switch points have moved completely from straight to curve (or vice/versa), in which case the Tortoise then cuts off it's own power.  Because of this style of operation, you'll need to connect a relay in between the DCS AIU and the Tortoise, so that you can control the Tortoise switch machines via DCS (and I think the same would apply for Legacy/TMCC as well).  There's a wiring diagram on the MTH website that describes this.

 

Best of luck... and most of all, have fun!

 

David

Last edited by Rocky Mountaineer
Candidly, I really don't think the difference in tie size will be noticeable at all. I used the Ross stuff for my yard but Atlas everywhere else. That big photo of my layout in the Nov CTT shows them both. I am sure either will work. Ross has those big multi switches which I really like for fanning out storage tracks. I am a big supporter of the Atlas track especially the way it all comes together with their curves but the Ross switches are very nice too. Last time we did a poll on this topic they were pretty evenly split between Atlas and Gargraves / Ross with the rest using MTH and Lionel.

Zett,

 

I have Atlas-O track, 45 Atlas-O No.5 switch tracks, and 12 RCS curved switch tracks on my layout. I used the Atlas-O switch machines on top of the table, and just had to mount a few to one of the alternate locations (on top) for clearance. So far I have had no significant problems with the switch machines or the Atlas switch tracks. I did have to put back in place the small plastic link on a couple of the machines right out of the box because they had slipped out of position.

 

My track spacing is 4-1/2 inches center-to-center throughout. I used Ø108 and Ø99 curves on my dual main, and have had no problems running my MTH Premier Big Boy on the inner track with 18” passenger cars on the outer track. I also run the MTH No.80 steam turbine at the same time as the Big Boy, and have no problems. The only problem has been running the MTH DDA40X on the outer main, and the Big Boy on the inner track. BTW, no problems with the Lionel Vision Challenger either.

 

As has been mentioned above, the Atlas No. 5 and & 7.5 switch tracks provide for a 4-1/2-inch spacing, and some bridges, such as the Atlas Dual Track Pratt Truss Bridge,  also have a 4-1/2-inch track spacing.

 

Good luck and keep us informed of your progress.

 

Alex

 

You can see my layout under construction here:

https://ogrforum.com/d...ent/2415514336550790

Thanks for the replies again, this is helping a lot. I thought everyone had agreed that 6" spacing was the way to go, but it sounds like if I run the super large engines on the outside line I should be ok. Hmm now that I look at this though Alex you said your using O99 and O108, I am wondering if the 4.5" spacing would be a problem using O72 and O81, just because of the tighter curve on the inside.

 

MikeCT thanks for the links, but I am completely lost lol. Once I get the products in my hand and figure out how to install 1 correctly I will be ok from there. So you went with O54 in the yards? I may have to look at that option as well, maybe I could fit in another siding.

Zett,  If you use Atlas track, as someone else's previous response noted, you can have concentric curves by using 072, 081, 090, 099, etc., track.  However, there are some things you can make to facilitate better clearance in the curves.  One is to vary the track curve size as you go into, and out of the curve, e.g., instead of using eight 081 curves sections to achieve a 180 degree curve, you can use eight pieces of track as follows: 090, 081, 081, 072, 072, 081, 081, 090.  This will provide a more realistic entry and exit of the curve, in about the same layout space.  Concentric larger or smaller curves would simply use the corresponding larger or smaller curve track.  Another way to have more clearance between concentric curved track is to start the inside curve .5" or 1" before the next outside curve.  Another way to achieve extra clearance is to add an extra .5" piece of straight track between curved sections occasionally, where needed.
 
I've used RR-Track software for more than six years on two layouts.  My experience is that no matter how good your track comes together on the computer, you have to be prepared to make minor adjustment with a good Dremel tool to insert or shorten track pieces.  Sometimes adjustments as small as .25" can make a big difference.  As I noted on my bpsouthwestern.com website on the Building the B&P page, I had to go back and make several adjustments in concentric curve spacing to ensure adequate clearance if, on a rare occasion, two trans with excessively overhanging locomotives/cars should pass at the same time.  I did not want to have any portion of track not able to handle all of my locomotives and/or rolling stock.  Best of luck, Bob 

Thanks for the replies again, this is helping a lot. I thought everyone had agreed that 6" spacing was the way to go, but it sounds like if I run the super large engines on the outside line I should be ok. Hmm now that I look at this though Alex you said your using O99 and O108, I am wondering if the 4.5" spacing would be a problem using O72 and O81, just because of the tighter curve on the inside.

 

MikeCT thanks for the links, but I am completely lost lol. Once I get the products in my hand and figure out how to install 1 correctly I will be ok from there. So you went with O54 in the yards? I may have to look at that option as well, maybe I could fit in another siding.

Zett, just to clear up any confusion... the previous post is correct in that the Tortoise machines receive power at all times -- usually 9-12 volts DC, and they simply stall out at the end of the throw.  Power polarity then needs to be reversed when moving the switch points in the opposite direction.  It's been a few years since I wired mine, so I apologize for misspeaking.   Thanks to the previous poster for refreshing my aging brain.

 

The point in my original post was intended to emphasize the fact that the Tortoise is NOT a momentary-contact type set-up like the Atlas-O or Ross (DZ-1000/2500) switch machines, and that's why we need the extra latching relay involved if we're gonna control the Tortoise with a momentary-style set-up like DCS's AIU or the Legacy/TMCC equivalent electronics.  Well worth the extra wiring effort, IMHO.

 

David

Still working on track planning... 

 

1. After watching Eric Siegel's Atlas switch video part 1, I am thinking of using the Atlas Terminal joiners. Anyone use these or have any experience with them?

 

2. I have a few outside curves on my layout that are O-80. Since Atlas does not make an O-80 switch, how do I solve this problem? I dont want the outside loop to have a curve tighter than O-80, so do I use a #5 switch and then custom cut a piece of O-80 curve?

 

3. It seems that some use O-54 switches for yards. Im correct in assuming then you need a switcher engine to run on these turnouts correct? Obviously you cannot take an engine with a minimum O-72 rating and run her through an O-54 switch... This also confuses me because Atlas makes a O-72 / O-54 curved switch, why not a larger one?

 

I started my project thinking I would use nothing smaller than O-72, seems like I am being pushed to smaller curves.

 

Thanks again for your responses.

`Zett,

 

". . . use a #5 switch and then custom cut a piece of O-80 curve?"

 

That's what I would do. Cutting the Atlas track is easily done with a cutoff wheel and a rotary tool, Dremel or otherwise. I used a lot of the pieces I had left over after cutting the tracks to fit RR-Track dimensions (± 1/32"), but some did not have a place, so I kept most of these. I kept some of the ties to use as loads, or as junk . . .

 

(Practice makes perfect)

  

Track Pieces 01 med crp DSC05433

 

Good luck!

 

Alex

Attachments

Images (1)
  • Track Pieces 01 med crp DSC05433

Zett....To try to help answer your question about the "O-54" dilemma.  Because I wanted more tracks in my yard, I broke down and decided to use O-54 turnouts.  Just like you, at first I worried about the locomotives that required O-72 curves.  Well, what I found out was that many of my O-72 locomotives didn't have a problem going through the O-54 switch because there simply was not enough of the O-54 curve for the wheels to bind before the locomotive entered straight trackage.  Regardless, I realized that prototypically large steamers would not be working the yard so using a tighter radius would be OK.  On the prototype, not all motive power could negotiate all trackage.  While it can be done, if you design your layout so that the largest locomotives can go everywhere...well....there is nothing wrong with that but you may limit yourself as far as being able to fit other elements into the track plan.  Heck...I have fun bringing a large locomotive into the yard throat, dropping off the train, and then bringing in a smaller switch engine to break up the train and shove the various cars into the yard sidings....  Bottom line, you have to decide what you want to do in the space you have to do it in....in other words, you decide on your "druthers"..

 

Alan

Post
The Track Planning and Layout Design Forum is sponsored by

AN OGR FORUM CHARTER SPONSOR
×
×
×
×
Link copied to your clipboard.
×
×